A focused strategic plan, not a full utility master plan. It is scoped deliberately to the obligations the City carries under FDEP Consent Order OGC No. 24-3045 and NPDES MS4 Permit No. FLS000003, and to the departments those obligations reach beyond Public Works and Utilities. Prepared following the strategic planning session held with the department.
Thirteen sections, seventeen figures and seven appendices. Section 12 is the one to read first if time is short.
Appendix A is bound in this document at the pages listed above. Appendices B to G are existing documents in the program record and are referenced rather than reproduced, so that this report stays at a length a Commission member will read.
Prepared at the direction of the Assistant City Manager following the strategic planning session held with the Public Works and Utilities Department.
On 26 May 2026 the Florida Department of Environmental Protection confirmed in writing that all eight items due within thirty days under its Stipulated Penalty Assessment of 21 April 2026 were complete. The administrative penalty of $62,852.92 had already been paid and receipt confirmed on the coordination call of 11 May 2026. That correspondence marks the end of the corrective action phase that had run since the Consent Order was executed on 12 August 2025.
This is a real achievement and it should be recorded as one. In roughly five weeks the department answered eight open items, filed eight supporting appendices, and closed a penalty assessment. Very few departments of this size move that quickly under that kind of pressure.
Closing the corrective actions did not reduce the work. It changed its nature. The eleven Standard Operating Procedures the City submitted to the Department commit the department to 135 recurring actionable items. Together with the two progress reporting obligations in the Consent Order, that is 658 separate actions in the first 180 day operating period and 1,326 in a full year, or about twenty six every week. The department currently fields a fraction of the staff that volume implies.
This plan does not ask the City to do more than it agreed to do. It sets out what the City already agreed to, counts it honestly, and identifies where continuity of service is at risk.
The plan makes three recommendations, in descending order of urgency and ascending order of cost.
| Recommendation | What it means in practice | |
|---|---|---|
| 1 | Close the order and hold it closed | Confirm the ordinance, adopt a standing reporting cadence, and settle the four asset counts. Section 12 sets out six actions in the next ninety days. Four of them cost nothing but a decision. |
| 2 | Advance a defined project list | Twelve projects at Section 7 that together satisfy the intent of the Consent Order rather than only its letter. Each is tied to an obligation, a funding route and a sequence position. |
| 3 | Commission a five year master plan | Section 9. The anchoring document that makes every future funding request defensible and stops the department funding compliance from crisis. |
Lenders and grant reviewers ask a single question before they ask anything else: is this project part of a plan. A city that answers yes is funded on the strength of the plan. A city that answers no is asked to justify each request from first principles, every time, and is usually funded last.
The City currently has an executed Consent Order, a scored funding application and eleven procedures. What it does not have is the document that connects them, prices them across five years and shows the revenue that carries the debt service. That document is the difference between reacting to regulators and programming the work.
Compliance programs do not usually fail because someone made a wrong decision. They fail because a person left, a report was not sent, a calendar entry was never made, and eight months later a letter arrives. That is precisely the sequence this City experienced between October 2025 and April 2026.
Appendix A sets out the current organization as far as it can be reconstructed from the record, a proposed organization, and the training and succession arrangements that would allow the program to survive the loss of any single person.
Why this plan exists, what it deliberately covers, and what it deliberately leaves out.
It reaches beyond Public Works. The obligations in the order and the permit touch the Building Department for permit and construction data, the City Attorney for the ordinance, Finance for the funding applications and the rate position, Information Technology for the systems that hold the record, and the Office of the City Manager for the reporting the Department receives. This plan is addressed to the Public Works and Utilities Department because that is where the obligation sits, but it cannot be delivered there alone.
Most municipal strategic plans take six to nine months and cover every function of a department. This one was produced in weeks and covers one thing. That was a deliberate choice made with the Director.
The reason is the clock. The City is operating under an executed Consent Order with enumerated obligations, fixed dates and stipulated penalties. A plan that arrives after those dates have passed is an academic exercise. The department needed a working instrument, not a study.
| Area | What it covers |
|---|---|
| Consent Order OGC 24-3045 | Every enumerated obligation in paragraphs 6 and 7, their dates, and their current status. |
| MS4 Permit FLS000003 | The permit parts the Consent Order cites, and the Standard Operating Procedures written to satisfy them. |
| The operating workload | Every recurring action the eleven submitted procedures commit the department to perform. |
| Funding readiness | Shovel ready position, lead service line program, State Revolving Fund and grant pathways. |
| Workforce and continuity | Whether the department can perform and evidence the work with the staff it has. |
This plan does not cover the sanitary sewer consent order with Miami-Dade DERM, the water treatment and distribution capital program beyond lead service lines, solid waste, roads outside the stormwater context, or the department's general administration. Each of those deserves its own plan. Folding them in here would have delayed a document the City needed immediately.
It also does not restate the Consent Order. The order is attached at Appendix D and it speaks for itself. This plan is about what the City has to do next.
It is written for the Director of Public Works and Utilities, to be carried into the City Manager's office and the Assistant City Manager's office. It is written in plain language so that a reader who is not an engineer can follow the argument and act on it.
A working session with the department, two whiteboards, and a deliberate refusal to start from a template.
This plan did not begin with a document review. It began with the Director and the department in a room, two blank whiteboards, and one question: why are we here.
The first board captured the diagnosis. Everything the department knew was wrong, written down in no particular order and then connected. The second board captured the response. Both are reproduced below as they were drawn, with nothing added and nothing removed.
Starting from the department's own words rather than a consultant template produced two things a template would have missed. First, the single word the department kept returning to was documentation, not funding and not staffing. Second, the response the department reached on its own was a process, not a request. Access the data, analyze it, transmit it. That is a workflow the City can own.
The corrective action phase closed on 26 May 2026. One item remains open and the operating clock is running.
| Item | Status | Note |
|---|---|---|
| Eight items in the April assessment | CLOSED | Confirmed complete by FDEP in writing on 26 May 2026. |
| Administrative penalty, paragraph 9 | PAID | $62,852.92. Receipt confirmed on the coordination call of 11 May 2026. |
| Erosion and sediment control ordinance | OPEN | Paragraph 6(c) viii. Was due 1 August 2026. The last item before a formal closure letter. |
| Bi-monthly progress report | OWED | Paragraph 6(e). Not cited in the April assessment, but still owed under the order. |
| Quarterly progress report | OWED | Paragraph 7. Same position. |
| Structural control inventory | 2030 | Paragraph 6(d). Five year obligation. Not yet started. |
The Department has said a formal closure letter will follow once the remaining item is complete. That letter is worth having. It is the document the City can put in front of the Commission, a lender or a grant reviewer.
A short assessment produced with the department during the planning session, not written afterward.
The strengths are real and recent. A department that closes eight regulatory items in five weeks is a department that can execute when it is pointed at something specific.
The weaknesses share one root. They are all about the record rather than the work. The City is doing more than it can currently prove, and proof is what the Consent Order asks for.
The single most important line in this figure is in the threats quadrant: loss of the position that holds the program. Every other threat has a mitigation that money or time can buy. That one does not.
What the eleven accepted procedures commit the department to perform, counted honestly.
It counts actions the City has already committed to in writing. It is not an estimate of effort produced by a consultant and it does not assume any new program.
It is also a floor rather than a ceiling. Four asset counts remain unsettled. Quarterly outfall inspections resolve to zero, sixteen or twenty a year depending on which City document is correct. Semi-annual inlet surveys resolve to 806, 900 or 1,546. Settling four numbers converts this from a range into a figure the City can budget against.
The chronic pressures that erode a compliance program, and the acute events that break it.
| Stress | How it shows up | What reduces it |
|---|---|---|
| Workforce continuity | A single position carries most of the program. Institutional knowledge is held in one head and is not written down anywhere the next person could find it. | Documented procedures tied to a training record, and a delivery model that does not depend on one person staying. |
| Limited funding | The department competes for general fund dollars against every other service. Compliance work has no natural constituency until something fails. | A five year capital and operating plan that shows the cost of the program and the cost of not running it. |
| Fragmented records | Inspection records, permits, GIS and correspondence live in separate systems. Every regulatory report is assembled by hand from four places. | One connected chain from field inspection to regulatory submittal. |
| Aging infrastructure | Lead and galvanised service lines remain in contact with the drinking water supply. Stormwater structures have no complete inventory. | The funded lead program, and the structural control inventory required by 2030. |
| Regulatory load | Two consent orders, one MS4 permit, county Chapter 24, and a drinking water rule all run at once, each with its own calendar. | A single compliance calendar with named owners. |
| Shock | Consequence | Current readiness |
|---|---|---|
| Loss of key staff | The compliance record stops. Reporting lapses. Penalties resume. | LOW No documented succession for the role. |
| Major storm event | Flooding, overflows, illicit discharge events, and a surge of reactive work that displaces scheduled inspections. | PARTIAL Procedures exist. Capacity to run them under surge does not. |
| Sanitary sewer overflow | Notification obligations inside 24 hours, and exposure under the second consent order. | PARTIAL Telemetry on six sites. Procedure is sound. |
| Stipulated penalty demand | Demandable at any time for any missed requirement in the order. | PARTIAL Eight items closed. Reporting cadence not yet in place. |
| Funding window closes | Federal lead funds move on a fixed cycle. Unclaimed allocations have already been returned once. | TIME LIMITED Application in progress. |
The pattern is consistent. The department has written good procedure. What it lacks is the capacity and the continuity to run that procedure through a shock without the record stopping.
Twelve projects that together satisfy what the Consent Order is trying to achieve, not only what it lists.
A Consent Order sets out the minimum a City must do to return to compliance. It does not describe a functioning program. The twelve projects below are what the department needs to satisfy the intent of the order and to stay satisfied once the order closes.
Each project is tied to an obligation, given a category and placed in sequence. Nothing here is speculative and nothing here is outside the scope of the order or the permit.
| Ref | Project | Category | Obligation | When | What it delivers |
|---|---|---|---|---|---|
| P-01 | Consolidated progress reporting | Compliance | 6(e), 7 | Now | One catch-up submittal covering every missed period, then a standing bi-monthly and quarterly cadence. |
| P-02 | Erosion and sediment control ordinance | Compliance | 6(c) viii | Now | Adoption and transmittal of the ordinance. The last item before a formal closure letter. |
| P-03 | Asset count and field verification | Data | 6(b) v, 6(d) | Now | Establish defensible counts for outfalls, inlets, structural controls and active construction sites. |
| Ref | Project | Category | Obligation | When | What it delivers |
|---|---|---|---|---|---|
| P-04 | Post-construction review procedure | Compliance | 6(b) i | Now | Write and file the procedure the compliance matrix certifies and the record does not contain. |
| P-05 | Training and awareness program | People | III.A.7.c, 9.c | Now | Ten to fifteen modules, recorded completion, refreshers. Closes the procedure five others depend on. |
| P-06 | Structural control inventory | Data | 6(d) i, ii | Year 1 to 2 | Complete inventory and inspection regime for structural controls and roadway collection structures. |
| Ref | Project | Category | Obligation | When | What it delivers |
|---|---|---|---|---|---|
| P-07 | Lead service line planning and design | Capital | LCRI | Now | Planning and design loan. Converts a scored application into fundable design. |
| P-08 | Building Department data chain | Data | 6(b) i, xv | Year 1 | Access, analyze and transmit permit data so construction records can be produced without manual assembly. |
| P-09 | GIS and asset mapping | Data | III.A.1 | Year 1 to 2 | Single custodian risk removed, field changes reflected in the atlas, counts held in one place. |
| Ref | Project | Category | Obligation | When | What it delivers |
|---|---|---|---|---|---|
| P-10 | Connected compliance system | Systems | All | Year 2 | One chain from field inspection to regulatory submittal. Retires manual report assembly. |
| P-11 | Stormwater capital and operating plan | Funding | 6(d), permit | Year 1 | Five year program separating capital from operating and showing the revenue that carries it. |
| P-12 | Water master plan, five years | Funding | LCRI, SRF | Year 1 | The anchoring document. Makes every subsequent funding request defensible. |
Seven of the twelve are already in progress in some form. The value of listing them together is not novelty. It is that a Commission or a lender can see one program rather than twelve unrelated requests.
| If this is done first | These become possible | Reason |
|---|---|---|
| P-03 Asset count | P-06, P-09, P-11 and the staffing case | Every per asset obligation is a frequency multiplied by a population. Without the population there is no workload figure, and without a workload figure there is no defensible budget request. |
| P-01 Reporting cadence | Everything, indirectly | It is the discipline that keeps the order closed. Without it the department is one missed period away from repeating April 2026. |
| P-02 Ordinance | The formal closure letter | The Department has said the letter follows once this item is complete. The letter is what the City shows a lender or a grant reviewer. |
| P-07 Planning and design | The construction phase | Construction money attaches to design. Until design exists the ten year program is not reachable. |
| P-12 Master plan | P-11 and every future request | Reviewers ask whether a project sits inside a plan before they ask anything else. |
| P-08 Data chain | P-10 Connected system | A connected system needs a source of permit data. The chain is the source. |
The order lists documents. Read as a whole it asks for something larger: a City that can inspect what it owns, record what it inspects, report what it records, and fund what the record shows it needs.
Projects P-01 through P-05 make the City compliant. Projects P-06 through P-10 make it capable. Projects P-11 and P-12 make it fundable. A department that completes only the first group will be back in front of the regulator when the next permit cycle begins.
Three tracks, one qualification argument, and a window that is open now.
Shovel ready is not a description of intent. It is a description of paperwork. A project is shovel ready when the scope is defined, the design is sufficiently advanced, the cost is defensible and the authorising resolution is in place. Until then it cannot be funded no matter how urgent it is.
The lead service line program is the closest the City has to shovel ready. The Request for Inclusion was signed on 15 May 2025 and scored in the highest acute public health risk category. The planning and design loan converts that into design, and design is what construction money attaches to.
| Route | What it offers, and what it asks for |
|---|---|
| Miami-Dade County and the Water and Sewer Department | The County and WASD hold technical capacity, funding relationships and a direct interest in the performance of the systems Opa-locka connects to. A written request for technical assistance, and letters of support against specific applications, cost the City nothing and materially strengthen every submission. This should be sought formally rather than relied on informally. |
| WIFIA, the federal Water Infrastructure Finance and Innovation Act | Longer terms and lower cost than most alternatives. The small community threshold is reachable if the City bundles its program rather than applying project by project. It has not been tested, and the assumption that Opa-locka is too small should be checked rather than accepted. |
Both routes benefit from the same preparation the rest of this plan calls for. A County letter of support and a WIFIA letter of interest both ask what the City has, what it plans and what it can repay, and all three of those answers come from the work in Sections 5 to 9.
| Step | Action | Why it comes in this order |
|---|---|---|
| 1 | Complete and file the planning and design loan | It is scoped, priced and scored. It is the nearest available money. |
| 2 | Confirm the five year water master plan | Lenders and grant reviewers ask whether a project sits inside a plan. Without one, each request looks reactive. |
| 3 | Establish the capital and operating plan | Separates what is capital from what is operating, and shows the debt service the revenue has to carry. |
| 4 | Pursue the construction phase | Ten year program. Only reachable once design exists. |
The one document that would change how every future funding request is received.
Everything in this plan points at the same conclusion. The department is managing a five year problem with one year instruments. A five year master plan is the instrument that matches the problem.
| Component | What it establishes |
|---|---|
| Asset inventory and condition | What the City owns, where it is, and what state it is in. Settles the four counts that currently gate the workload model. |
| Level of service | What the City has committed to, at what frequency, drawn from the eleven procedures rather than invented. |
| Capital program, year by year | Which projects in which year, with scope, schedule and budget against each. The Consent Order obligations sit inside it rather than beside it. |
| Operating program | The recurring cost of running the compliance program, separated from capital so neither hides the other. |
| Funding and debt service | Which projects are grant funded, which are loan funded, and what revenue carries the debt service across the period. |
| Rate and revenue position | Whether current revenue supports the program, and if not, by how much it falls short. |
At present each request is judged on its own merits and against every other request the City makes. With a master plan in place the question changes from whether this particular project is worth funding to whether the City is executing a plan it has already published. That is a materially easier question for a reviewer to answer yes to.
It also protects the department internally. A project inside an adopted plan is difficult to defer without an explicit decision to depart from the plan. A project outside one is deferred without a decision being recorded.
The Consent Order runs to 2030 for the structural control obligations. The lead service line program runs to 2036. Neither fits inside an annual budget cycle. A five year plan is the shortest horizon that can hold both, and it is the horizon the funding agencies work to.
Every date the department is currently working to, in one table.
| When | What | Authority | Status | Note |
|---|---|---|---|---|
| 1 August 2026 | Erosion and sediment control ordinance adopted | Consent Order 6(c) viii | PAST | The last item from the April assessment. |
| Every two months | Progress report to FDEP | Consent Order 6(e) | OWED | Never filed. Not cited in the April assessment. |
| Every quarter | Progress report with supporting documentation | Consent Order 7 | OWED | Never filed. |
| 22 November 2026 | End of the first 180 day operating period | Operating clock | DUE | Everything in Section 5 has to be demonstrable. |
| 31 December 2026 | Emergency Response Plan | AWIA | DUE | Statutory deadline. |
| When | What | Authority | Status | Note |
|---|---|---|---|---|
| Annual | MS4 Annual Report | Permit FLS000003 | RECURRING | Filed for 2021, 2022, 2023 and 2025. |
| Annual | Water Accounting Data Form | FDEP | RECURRING | Was due 30 April 2026. |
| 12 August 2030 | Structural control inventory and inspection | Consent Order 6(d) | FUTURE | Five year obligation. Not started. |
| September 2036 | Lead service line program complete | LCRI | FUTURE | Approximately one year ahead of the federal deadline. |
Two entries on this table are shown as owed rather than late. The Department did not cite the progress reports in its April assessment, so no penalty has been assessed against them. They remain obligations under the order and they are the first thing a reviewer looks for.
A standing reporting cadence with a named owner. Not a new system and not a new position. A calendar entry, a template, and one person accountable for pressing send. Every date in the table above is protected by that single discipline, and the absence of it is what produced the April assessment.
Where the department gets the most protection for the least money.
| # | Action | Cost | What it returns |
|---|---|---|---|
| 1 | Settle four asset counts | NONE | Converts the entire workload model from a range to a figure. Makes the staffing case, the budget request and the progress report all defensible at once. Nothing else on this list returns as much. |
| 2 | Adopt a reporting cadence | NONE | Removes the single failure that produced a penalty assessment. Protects every date in Section 8. |
| 3 | Confirm the ordinance | NONE | Releases the formal closure letter. A document the City can show a lender, a grant reviewer or the Commission. |
| 4 | File the planning and design loan | STAFF TIME | Opens a $17.2 million program with roughly $8.43 million potentially forgivable. The highest dollar return available to the department. |
| 5 | Document the succession | LOW | Removes the single largest threat in the SWOT. Protects continuity of service when, not if, the position turns over. |
| 6 | Connect the compliance chain | CAPITAL | Turns every field inspection into a regulatory record automatically. Removes manual assembly from every report. Highest cost on this list and the highest ongoing saving. |
Stipulated penalties under paragraph 10 run at $200 per day and are demandable at any time after a requirement is missed. That is $6,000 a month and $73,000 a year. Paragraph 17 allows judicial penalties of up to $15,000 per day per violation. Paragraph 14 waives the Department's right to pursue pre-order violations only for as long as the City remains in complete compliance.
The first three actions in the table above cost nothing and remove most of that exposure. That is an unusual position to be in and it will not last indefinitely.
Six actions in the next ninety days. Four of them cost nothing but a decision.
Five of the six actions above are already in progress in some form. The department has procedures written, an application scoped, and a regulator relationship that is working. What is at risk is not the starting of this work. It is the continuing of it.
Compliance programs do not usually fail because someone made a wrong decision. They fail because a person left, a report was not sent, a calendar entry was never made, and eight months later a letter arrives. That is precisely the sequence this City experienced between October 2025 and April 2026, and it is the sequence this plan is designed to prevent from repeating.
Where this leads if the immediate actions are taken.
The department can answer any question a regulator asks from a system rather than from memory. The capital program is funded from a plan rather than from crisis. Lead service lines are being replaced on a schedule that finishes ahead of the federal deadline. Structural controls have a complete inventory and an inspection record. And the program continues when any individual leaves.
None of that requires a new department. It requires the six actions in Section 10, taken in the next ninety days, and then sustained.
The City of Opa-locka has been described in its regulatory correspondence in terms of what it has failed to submit. That is a fair description of the file and an unfair description of the department. In the five weeks between 21 April and 26 May 2026 this department closed eight regulatory items and a penalty assessment. The capability is present. What has been missing is the connective work between the capability and the record, and that is a solvable problem.
Each attachment stands alone and can be read without the plan.
| Attachment | What it contains | |
|---|---|---|
| A | Sheet OP-01 Proactive Inspection Program | Cost of the inspection function, level of service required by the procedures, and the decision items arising. |
| B | Sheet OP-02 Consent Order Compliance Register | Every enumerated obligation in the order, what answers it, and its current status. Ten pages. |
| C | Sheet OP-03 SOP Register and Workload | The eleven procedures, what each does, and the volume of recurring work each carries. Two pages. |
| D | Consent Order OGC 24-3045 | Executed 12 August 2025. Thirteen pages. |
| E | Stipulated Penalty Assessment | FDEP, 21 April 2026. Eight items due within thirty days, plus the ordinance milestone. |
| F | City response and FDEP confirmation | City letter of 20 May 2026 with eight appendices, and the Department confirmation of 26 May 2026. |
| Prepared for | Mr. Airia Austin, Director of Public Works and Utilities, City of Opa-locka |
| Prepared by | APAS |
| Revision | Rev A, 16 August 2026 |
| Basis | Strategic planning session held with the department, Consent Order OGC No. 24-3045, MS4 Permit No. FLS000003, the eleven Standard Operating Procedures submitted January 2026, and FDEP correspondence to 26 May 2026. |
| Status | For discussion. Figures shown as ranges remain open pending the four asset counts in Section 5. |
Prepared at the direction of the Assistant City Manager. Submitted to the Office of the City Manager for review. Signature indicates receipt and acknowledgment of the findings, not approval of any expenditure.
The current structure as far as the record allows it to be reconstructed, and a proposed structure.
The single largest threat identified in Section 4 is the loss of the position that carries the compliance program. This appendix sets out why that risk exists structurally, and what structure would remove it.
| Observation | Consequence |
|---|---|
| Compliance sits inside operations | Inspection, recording and reporting compete with daily field demands. When a storm arrives, the record is what gets deferred. |
| No single owner of the record | Reports are assembled by whoever is available, from four systems, when someone remembers. That is how the April assessment happened. |
| GIS is shared and unbacked | One custodian with other duties holds the asset data that four obligations depend on. |
| Consultants engaged task by task | Useful for delivery, but no standing accountability for continuity. When the task ends, the knowledge leaves. |
| No documented deputy anywhere | Every function has a first name against it and no second name. |
| Function | Status | Why it is proposed |
|---|---|---|
| Compliance Manager | NEW | Owns the compliance calendar, the reporting cadence and the record. This is the role whose absence produced the April 2026 assessment. It does not need to be a new hire in every scenario, but it does need to be a named person whose primary duty is the record rather than the field. |
| MS4 inspectors | EXISTING | Reporting to compliance rather than to operations, so that scheduled inspection is not displaced by reactive work. The workload at Section 5 is what sizes this team. |
| Records and reporting | NEW | Produces the bi-monthly and quarterly submittals and maintains the evidence file. Can be part time or shared, but must be somebody nominated in writing. |
| Function | Status | Why it is proposed |
|---|---|---|
| Operations Superintendent | EXISTING | Unchanged. Field crews continue to run litter, sweeping and roadway maintenance. The change is that their output feeds the record automatically rather than on request. |
| Capital and Funding | NEW OR SHARED | Owns the State Revolving Fund applications, grant capture and the capital plan. At present this work is done by whoever is available at the time, which is why funding windows are a risk rather than an opportunity. |
| Dotted line relationships | FORMALIZE | GIS and IT, Building Department permit data, the City Attorney and Miami-Dade DERM. None of these should move into Public Works. All of them need a named contact and a service expectation in writing. |
The Consent Order requires training under Permit Parts III.A.7.c, III.A.7.d and III.A.9.c. The department currently satisfies this through occasional sessions. That meets the letter of the requirement and does very little for continuity.
| Element | Cadence | What it achieves |
|---|---|---|
| Module library | Ten to fifteen modules | One module per procedure area. Every new procedure or Consent Order requirement becomes a module rather than a memo. |
| New starter program | Within 30 days | A new employee reaches competence on a schedule rather than by sitting next to somebody. |
| Annual refresher | Each January | Satisfies the permit and refreshes the whole department at a predictable point in the year. |
| Toolbox talks | Quarterly | Short, specific and recorded. March, June, September and December. |
| Completion record | Continuous | Recorded in the system of record. Training that is not recorded did not happen as far as a regulator is concerned. |
The training obligation is currently the weakest link in the procedure set. One procedure that five others depend on for their training frequency is not present in the submitted set at all.
| Measure | What it looks like in practice |
|---|---|
| Named deputy for every function | A second name against each box in Figure 9, recorded and known to the person concerned. |
| Written procedure for every recurring action | The 135 items at Section 5, each with a procedure a competent stranger could follow. |
| Records in a system, not in a person | Inspection, training and reporting records held where the next person can find them without asking anyone. |
| Cross training across functions | Inspectors who can produce a report and reporting staff who have been in the field. |
| Continuity through the contract layer | Where the City chooses to use supporting firms, the obligation to maintain the record travels with the contract rather than with the individual. |
The structure in Figure 9 should be judged against one question. If the person who currently holds the compliance program resigned tomorrow, how long before the Department noticed. Under the current structure the honest answer is one reporting cycle, which is sixty days. Under the proposed structure it is no time at all, because the record continues without them.
APAS Consulting works with water, wastewater and stormwater utilities on regulatory compliance, asset and data programs, capital planning and funding strategy. We build the record a utility needs to prove what it does, and the plan it needs in order to fund what comes next.
| Document | Regulatory Compliance Strategic Action Plan, FDEP Consent Order OGC No. 24-3045 and NPDES MS4 Permit No. FLS000003 |
| Revision | Rev C, issued 16 August 2026 |
| Status | Draft for discussion with the Office of the City Manager |
| Supersedes | Rev A and Rev B, issued as Strategic Plan Report. Retitled at Rev C to state the scope accurately |
| Review method | Open this file in a browser and use the review toolbar at the top of the page to edit text, attach notes to any block, and export those notes |
This report was prepared for the sole use of the City of Opa-locka. It draws on the documents supplied to APAS Consulting and on the strategic planning session held with the Public Works and Utilities Department. Where the record was incomplete, the report says so and marks the item for confirmation rather than filling the gap. Figures reconstructed from correspondence are labeled as reconstructions. Nothing in this report constitutes legal advice or a representation to the Florida Department of Environmental Protection.